Progress and final invoices: how to get them right
On larger jobs you do not have to wait until the end to get paid. Progress invoices protect your cash flow – the final invoice settles everything cleanly at the end.
- You may request instalments for work already performed (§ 632a BGB).
- For construction contracts with consumers, instalments are capped at 90 % of the total price (§ 650m BGB).
- VAT on an instalment is usually due as soon as the payment is received.
- The final invoice shows the complete work and deducts all paid instalments including their VAT.
Progress invoice, partial invoice, final invoice – the difference
| Invoice | What for? | When? |
|---|---|---|
| Progress invoice (Abschlagsrechnung) | share of the price for the work done so far | during the work, e.g. by construction progress |
| Partial invoice (Teilrechnung) | a completed part of the work that can be accepted separately | when a part is finished and accepted |
| Final invoice (Schlussrechnung) | the complete work, minus all instalments | after completion and acceptance |
When are instalments allowed?
Under § 632a BGB you can request instalments equal to the value of the work already performed in line with the contract. The easiest way is a payment plan in the quote, e.g. 30 % at the start, 40 % after the shell, 30 % after acceptance. Document progress with photos and measurements – that answers questions before they are asked.
For consumer construction contracts there is an additional rule: instalments may not exceed 90 % of the agreed total price, and with the first instalment the consumer can ask for 5 % security (§ 650m BGB). Contracts under VOB/B have their own rules (§ 16 VOB/B).
VAT: the most common mistake
For payments received before completion, VAT is usually due when the money comes in. That is why every progress invoice shows VAT. In the final invoice you deduct the instalments received and the VAT they contain. If you only deduct gross amounts or show the VAT twice, you may end up owing it twice (§ 14c UStG).
Worked example
Job worth €20,000 net, 19 % VAT:
| net | VAT | gross | |
|---|---|---|---|
| 1st instalment | €6,000.00 | €1,140.00 | €7,140.00 |
| 2nd instalment | €8,000.00 | €1,520.00 | €9,520.00 |
| Final invoice: total work | €20,000.00 | €3,800.00 | €23,800.00 |
| minus paid instalments | − €14,000.00 | − €2,660.00 | − €16,660.00 |
| Amount still due | €6,000.00 | €1,140.00 | €7,140.00 |
Final invoice checklist
- All mandatory details of a normal invoice (number, date, service period, tax number or VAT ID)
- The complete work performed with the total amount
- Every progress invoice with number, date, net, VAT and gross
- The amount still due and the payment deadline
- Change orders and extra work shown separately
Status: September 2026. This guide explains German rules in practical terms and does not replace legal or tax advice.
With Workalife Premium you create progress invoices from a quote as a percentage or a fixed amount. The final invoice deducts all instalments automatically including VAT – and you can never bill more than the order total.
You might also like
E-invoicing in Germany: what trades and service businesses must do now
Receiving since 2025, sending from 2027/2028: timeline, exceptions, formats and checklist.
Read more →Writing quotes that get accepted
Structure, validity, estimate or fixed price – and how to follow up properly.
Read more →Payment reminders and late interest: how to get your money
Default, late interest, the €40 flat fee, court payment orders and limitation – with an example.
Read more →From the guides straight into practice
Try Workalife free for 7 days – no credit card.