Guide

Progress and final invoices: how to get them right

Reading time approx. 5 minutes

On larger jobs you do not have to wait until the end to get paid. Progress invoices protect your cash flow – the final invoice settles everything cleanly at the end.

Key points
  • You may request instalments for work already performed (§ 632a BGB).
  • For construction contracts with consumers, instalments are capped at 90 % of the total price (§ 650m BGB).
  • VAT on an instalment is usually due as soon as the payment is received.
  • The final invoice shows the complete work and deducts all paid instalments including their VAT.

Progress invoice, partial invoice, final invoice – the difference

InvoiceWhat for?When?
Progress invoice (Abschlagsrechnung)share of the price for the work done so farduring the work, e.g. by construction progress
Partial invoice (Teilrechnung)a completed part of the work that can be accepted separatelywhen a part is finished and accepted
Final invoice (Schlussrechnung)the complete work, minus all instalmentsafter completion and acceptance

When are instalments allowed?

Under § 632a BGB you can request instalments equal to the value of the work already performed in line with the contract. The easiest way is a payment plan in the quote, e.g. 30 % at the start, 40 % after the shell, 30 % after acceptance. Document progress with photos and measurements – that answers questions before they are asked.

For consumer construction contracts there is an additional rule: instalments may not exceed 90 % of the agreed total price, and with the first instalment the consumer can ask for 5 % security (§ 650m BGB). Contracts under VOB/B have their own rules (§ 16 VOB/B).

VAT: the most common mistake

For payments received before completion, VAT is usually due when the money comes in. That is why every progress invoice shows VAT. In the final invoice you deduct the instalments received and the VAT they contain. If you only deduct gross amounts or show the VAT twice, you may end up owing it twice (§ 14c UStG).

Worked example

Job worth €20,000 net, 19 % VAT:

netVATgross
1st instalment€6,000.00€1,140.00€7,140.00
2nd instalment€8,000.00€1,520.00€9,520.00
Final invoice: total work€20,000.00€3,800.00€23,800.00
minus paid instalments− €14,000.00− €2,660.00− €16,660.00
Amount still due€6,000.00€1,140.00€7,140.00

Final invoice checklist

  • All mandatory details of a normal invoice (number, date, service period, tax number or VAT ID)
  • The complete work performed with the total amount
  • Every progress invoice with number, date, net, VAT and gross
  • The amount still due and the payment deadline
  • Change orders and extra work shown separately

Status: September 2026. This guide explains German rules in practical terms and does not replace legal or tax advice.